UGANDA’S ENERGY SECTOR STANDS AS EAST AFRICA’S FINEST

Date:

Share post:

Amidst a multitude of problems that Uganda faced, inadequate infrastructure was particularly serious before the NRM came on to the scene.

The country faced huge infrastructural gaps ranging from rampant electricity outages (load shedding), roads with potholes as well as few, expensive and unreliable telephone services.

After securing the country and working on a minimum economic recovery  program,  NRM  embarked  on  a development agenda, starting with closing the infrastructure gap in order to provide a foundation for development-oriented investment.

Productivity in every  sector  of  the  economy  is affected by the quality and performance of the country’s infrastructure, making it critical in competitiveness and ability to harness national, regional and global potential.

ENERGY INFRASTRUCTURE AS UGANDA’S STRONGHOLD

NRM inherited  a  country  with  hydro-electricity  generation  capacity  of  150  megawatts (MW) in FY1986/87 and only 60MW was being generated. This low electricity generation affected development and in particular industrialization.

In 2005, a decision was taken to invest in power generation so as to stem low supply. By the end of 2021, hydropower generation will stand at 1,868MW with the commissioning of Karuma (600MW).

NRM has also promoted other sources of energy including solar, geothermal, nuclear, thermal and bagasse energy. We are currently faced with a ‘good problem’ — surplus electricity. Total demand including exports was 680MW in June 2020, providing a surplus of close to 1,160MW. However, this surplus will be no more with increased industrialization, improved transmission, reduced costs, and  efficiency  in  distribution.  We are now dealing  with  the  challenges  of industrialization, transmission, distribution and cost.

POWER GENERATION: KEY POINTS

Hydropower generation will soon stand at 1,868MW with the commissioning  of  Karuma.  Construction of  Isimba  Dam  (183MW)  and  Ayago  II  Dam (42MW)  was  completed.  Karuma  Dam  (600MW)  works  were  at  98%  by  July  2020,  while the construction of substations and transmission lines is at 80%. The following small dams were commissioned;

COMMISSIONED DAMS

Kikagati 14.0 MW

Kyambura 7.6 MW

Lubilia  5.4 MW

Muvumbe 6.5 MW

Ndugutu 5.9 MW

Nkusi  9.6 MW

Nyamagasani I 15.0 MW

Nyamwamba 9.2 MW

Rwimi 5.54 MW

Sindila 5.25 MW

Situ II 16.5 MW

Situ I 5.0 MW

Tororo Solar  10.0MW

Waki 4.8 MW

TOTAL 120.28

DAMS ARE UNDER CONSTRUCTION

Achwa I (41MW)

Bukinda (6.5MW)

Busitema University Solar Power (4MW)

Kakaka (4.6MW)

Muyembe (6.9MW)

Muzizi (44MW)

Nyagak III (5.5MW)

Nyamagasani II (6MW

TOTAL 118.5

RURAL ELECTRIFICATION PROGRAM

Access to electricity is at the  heart  of  socio-economic  development.  It impacts on a  wide range of development indicators, including health, education, food security, gender equality, livelihoods and poverty reduction. Whoever grew up in  a village  remembers a life without  electricity. Some villages are now connected to the national grid and have steady supply of power. More villages are to be connected over the next five years.

There was a time of intermittent power cuts or load shedding. People had become used to that and it became a way of life. Today, any slight failure in power supply upsets everyone  and  is  considered  a  big  issue.  This confirms  that  there  is  a  steady  supply  of electricity, which people are now used to. NRM knows that providing electricity to all Ugandans is about serving humanity.

Without electricity, the provision of modern public health services becomes a daunting task. With lights at night, all children can study under similar conditions. Many now have TVs, not only for entertainment, but also for learning more about the rest of the world. With electricity, the use of electrical appliances such as fridges is on the rise.  Furthermore, appliances like fridges, salon equipment and cookers are being used by many Ugandans to generate incomes, which explains the need for a steady supply of electricity.

ELECTRIFYING DISTRICTS

By 1986, only 20 (about half) out of  39  district  headquarters  were  connected  to  the national  grid.

Today, only four (4) i.e.

Kaabong

Karenga

Kotido

Buvuma

Out of  146 districts and cities, only 4 districts are not yet connected. Work on taking power to Kaabong and Kotido is ongoing and will be completed in 2021.

The Government  is  also  going  to  look  for  approximately  Ush45  billion required to supply both Buvuma and Sigulu islands with electricity.

To increase  rural  electrification,  NRM  has  constructed  over  14,820km  of  Medium  Voltage (MV)  power  lines  and  approximately  10,000km  of  Low  Voltage  (LV)  power  distribution lines. This has translated into the connecting of over 1,000,000 consumers onto the national grid.

According to the Uganda Bureau of Statistics Baseline Survey of 2019, access to electricity has improved from 20% (on grid) in 2015/16 (it was 7% in 1986)  to 51% (on and off grid) in 2019/20.

The  51%  comprises  24%  access  to  the  national  grid  and  27%  access  through  offgrid (through mini-grids, solar home systems and others).

In  addition,  about  6,000km  of  MV  power  lines  and  5,000km  of  LV  power  lines  are  under implementation  with  1,500km  of  MV  power  lines  and  2,000km  of  LV  power  lines  under procurement.

ELECTRIFYING SUB-COUNTIES

In October 2019, NRM commenced on the Project for Bridging the Demand Supply Balance Gap  through  the  Accelerated  Rural  Electrification  Programme  that  is  supplying electricity to sub-county headquarters.

Under  the  project,  over  4,000km  of  MV  networks  and  over  6,000km  of  LV  networks shall  be  constructed  to provide electricity to  620 unserved  sub-county  headquarters countrywide.

These include 558 sub-county headquarters, 52 town councils and 10 division headquarters. Construction  started  in  October  2019  in  20  districts:  Kumi,  Kapchorwa,  Namutumba, Isingiro, Kassanda, Kyegegwa, Kibaale, Omoro, Otuke, Madi-okolo, Arua, Adjumani, Kiboga, Kanungu, Bundibugyo, Agago, Buyende, Bukedea, Kole and Apac.

EASING CONNECTING POWER TO HOMES

In order to increase  the consumption of  electricity, NRM is  making connections to homes easier and affordable.

Under this policy which started in 2018, the Government subsidizes the cost of electricity connection materials, enabling citizens  who  are  ready  for electricity consumption to benefit. Over 300,000 household connections are targeted annually.

GRID INTENSIFICATION

Alongside the grid  extension  projects,  the  Government  is  also  implementing  grid intensification  and  densification  projects  aimed  at  connecting  areas  with  suppressed demand within the existing national grid footprint. These projects target the connection of  underserved  load  centres  and  centres  within  a  2km  footprint  of  the  existing  grid.  This will  be  through  transformer  injections,  expansion  of  the  LV  reticulation  network  and  short expansions of the medium voltage network, mainly targeting highly populated areas such as municipalities, divisions and busy trading centres countrywide. NRM is also facilitating the evacuation of power from various small hydropower plants countrywide  through  the  get-fit  programme.  Over  70%  of  these  projects  have  been completed, with the  remaining currently under construction and  shall be  due for completion by the end of 2020.

TRANSMISSION & CONNECTIONS

The following transmission projects were completed:

Kawanda-Masaka T-Line 220kV, 137km line.

Kawanda and Masaka substations.

Nkenda-Fort Portal 220kV line.

Fort Portal-Hoima line and associated substations.

Isimba- Bujagali Interconnection project 132kV, 41km line.

Bujagali-Tororo 220kV, 127km.

Mbarara – Mirama 220kV, 66km line.

Mbarara-Nkenda 132kV, 160km line.

132kV  Kawanda-Kapeeka,  54km  transmission  line  and  20MVA  substation  at  Kapeeka.

Tororo – Opuyo – Lira 132kV, 260km transmission line.

Iganga 2x40MVA substation, Mukono 3x60MVA substation.

132kV Iganga T-off, 10km transmission line.

132kV Mukono T-off, 5km transmission line.

Additional transformation capacity on grid installed at Kawanda substation (40MVA), Kampala North (40MVA) and Lira (40MVA).

Queensway substation, construction of substations and transmission lines to four   Industrial Parks is  as  follows:  Iganga  and  Mukono  substations  were  completed;  Luzira substation  is  at  98%;  Mukono  Industrial  Park,  132kV  transmission  line  (5km)  and  Iganga industrial park, 132kV double circuit transmission line (12km)  completed.

As of June 2020, the following transmission projects were at various stages of implementation:

Karuma-Kawanda 400kV 254km, Karuma-Lira 132kV 75km, and Karuma-Olwiyo 400kV 60km lines  plus  associated  substations.  Construction ongoing  at  96%  completion; and projected completion in November 2020.

Karuma 400/132kV Substation is at 58%

Kawanda 400/220kV substation is at 60%.

Lira Substation is at 50%.

Bujagali Substation is at 82%.

Tororo Substation is at 87%.

Mbarara Substation is at 98%.

132kV  Mirama-Kabale  transmission  line,  80km  —  Procurement  of  contractor  was completed. Works will be completed within two years.

Mirama Substation at 75%.

Mutundwe-Entebbe  132kV,  24km  —  Construction  work  commenced.  To  be completed by December 2020.

Opuyo substations upgrade — Construction work ongoing.

132kV  Opuyo-Moroto  transmission  line,  168km  and  associated  substations  at  Moroto and Opuyo — Work has started and will be completed by December 2020.

132kV Lira-Gulu-Nebbi-Arua transmission line, 293km and  associated  substations – Procurement of contractor was completed. Works will be completed within two years, by mid-2022.

400kV Masaka-Mbarara transmission line, 135km —  Procurement of contractor is ongoing.

Gulu  –  Agago  132kV  overhead  transmission  line  and  associated  132/33kV  substations project  —  Procurement  of  contractor  is  at  final  stages.  The works  will  be  completed within two years of commencement.

132 kV  Mbale-Bulambuli  transmission  line  —  technical  feasibility  studies  were completed.

Procurement of the contractors to undertake construction  works  for  the  132kV  Lira–Gulu–Nebbi–Arua  transmission  line  and  associated substations  was  concluded  in  March  2020.

The  project  sites  were  handed  over  to  the contractors  in  August  2020.  Construction is  expected  to  be  completed  by  the  end  of 2022.

The line will not only connect West Nile to the national grid, but also provide power supply reliably to northern Uganda as follows:

Construction of  301km  of  132kV  Lira–Gulu–Nebbi–Arua  transmission  line.  The line  will have capacity to supply not less than 200MW.

A switchyard at Kole to enable the line connect to the national grid.

A substation in Gulu with the capacity to supply 80MVA.

A substation in Nebbi with the capacity to supply 40MVA. l

A substation in Arua with the capacity to supply 80MVA.

33kV short power lines connecting substations to the existing  distribution network.

Construction  of  the  400kV  Karuma–Olwiyo  transmission  line  with  a  substation  at  Olwiyo nearing completion. This line is being constructed under the Karuma Hydropower Project.

The  132kV  Lira–Gulu–Nebbi–Arua  transmission  line  will  connect to Olwiyo substation and, therefore, West Nile (Nebbi and Arua substations) will have a second option of getting power from Karuma through Olwiyo substation.

 

Related articles

UPDF and Zimbabwean Defence Forces Agree to Increase Collaboration on Regional Security

The Ugandan People's Defence Forces (UPDF) and the Zimbabwe Defence Forces (ZDF) have agreed to enhance their collaboration....

Parliamentary Health Committee Supports Proposal to Restrict Surrogacy to Married Couples Only

The Parliamentary Health Committee’s legal Officer, Jackie Guma has supported the barring of Assisted Reproductive Technology Services (ARTs)...

Bobi Wine Begs Eddy Kenzo for Support in Overturning Music Ban and Resuming Stage Performances

Robert Kyagulanyi, popularly known as Bobi Wine, has approached Eddy Kenzo, the President of the Uganda National Musicians...

Uganda-Kenya Expressway to Improve Transport Services Among East African Community States

The East African Community (EAC) Deputy Secretary General in charge of Infrastructure, Productive, Social, and Political Sectors, Hon....